Additional Residential Units (ARUs) in Ontario: Zoning, Building Code and Permits

Additional Residential Units (ARUs), also known as secondary suites, second units, accessory apartments or additional dwelling units, are becoming increasingly common across Ontario. These units may be located within an existing detached house, semi-detached house, townhouse, or in some cases within an accessory structure such as a garden suite.

Recent changes under Bill 23, the More Homes Built Faster Act, 2022, have expanded zoning permissions for additional residential units. However, zoning permission does not remove the requirement to comply with the Ontario Building Code, municipal zoning by-laws, fire safety requirements, servicing requirements and building permit procedures.

 

Bill 23 and Additional Residential Units in Ontario

Bill 23 introduced important planning changes allowing more residential units on many urban residential lots in Ontario. In general, up to three residential dwelling units may be permitted on a parcel of urban residential land, depending on municipal zoning, servicing, lot conditions and the location of the units.

It is important to understand that Bill 23 is primarily a planning and zoning change. It does not exempt a project from the Ontario Building Code, Ontario Fire Code, municipal registration requirements, zoning setbacks, parking requirements, conservation authority approvals or servicing limitations.

Ontario Building Code 2024: House vs. Small Building

Under the Ontario Building Code, a house generally means a detached house, semi-detached house or row house containing not more than two dwelling units. This distinction is critical for ARU projects.

Total Number of Dwelling Units
Typical Classification
General Design Impact
One dwelling unit
Single dwelling house
Standard residential requirements apply.
Two dwelling units
House with secondary suite / ARU
Part 9 or Part 11 may apply depending on the age and scope of work.
Three or more dwelling units
Small building / multi-unit residential
More stringent architectural, fire separation, exiting and mechanical requirements may apply.

Architectural Requirements for Secondary Suites and ARUs

Fire Separation

Fire separations are required between dwelling units and between dwelling units and shared spaces. The required fire-resistance rating depends on the building classification, existing construction, age of the house, and applicable provisions of the Ontario Building Code.

Exits and Egress

Each dwelling unit must have safe exit access. Basement units require careful review of stairs, exterior doors, egress windows, headroom and travel distance. Municipal zoning may also affect the location of below-grade entrances.

Ceiling Height and Layout

Existing basement conditions must be reviewed carefully. Ceiling height, beams, ducts and bulkheads can impact whether a basement is suitable for a legal secondary suite.

Sound Separation

Sound separation between units is recommended and may include insulation, resilient channels and gypsum board assemblies.

Mechanical, Plumbing and Electrical Requirements

Heating Systems

Each dwelling unit must have adequate heating. This may include shared systems with zoning controls, separate HVAC systems or heat pumps depending on the design.

Ventilation

Proper ventilation is critical. Kitchens and bathrooms must be exhausted, and in many cases HRV or ERV systems are required to maintain indoor air quality.

Duct Penetrations and Fire Protection

Where ducts pass through fire separations, fire dampers or other fire protection measures may be required depending on the design and applicable code provisions.

Plumbing

Additional kitchens and bathrooms increase demand on plumbing systems. Drainage, water supply, sump pumps and backwater valves should be reviewed.

Electrical

Electrical systems must comply with ESA requirements. Panel capacity, smoke alarms, carbon monoxide alarms and potential separate metering should be reviewed.

Municipal Zoning Requirements for ARUs in Ontario

Each municipality has its own zoning requirements, terminology and approval process. The following provides a general overview.

Municipality
Common Term
General Permission
Key Notes
Toronto
Secondary Suite / Multiplex
Permitted; Multiplex up to 4 units
Subject to zoning, fire separation and permits.
Mississauga
Second Unit
Permitted subject to zoning
Registration required.
Brampton
ARU
Second and third units permitted
Registration and side yard access required.
Markham
Second Suite
Permitted in certain zones
Zoning review required.
Vaughan
Secondary Suite
Permitted with restrictions
Parking and size limits apply.
Richmond Hill
ARU
Up to three units possible
Side yard access and parking required.
Oakville
Accessory Apartment
Permitted
Zoning certificate required.
Burlington
ARU
Permitted
Zoning clearance required.
Oshawa
Accessory Apartment
Up to three units possible
Registration required.
Whitby
Accessory Apartment
Permitted
Registration required.
Ajax
Accessory Apartment
Permitted
Survey and grading may be required.
Pickering
ADU
One or two units permitted
Registration required.
Milton
Secondary Suite
Permitted
Parking and servicing required.
Newmarket
ADU
Permitted
Registration and parking required.
Caledon
Accessory Apartment
Limited by zoning
Septic and conservation review may apply.
Aurora
Secondary Unit
Permitted
Registration required.
Georgina
Accessory Apartment
Permitted
Septic capacity review required.
Whitchurch-Stouffville
ARU
Up to three units
Fully serviced areas only.
King
ADU / ARU
Permitted with restrictions
Access and parking required.

For a detailed comparison of parking-space dimensions, accessible parking requirements, garage clearances, drive aisle widths, tandem parking provisions, and municipality-specific design standards across Toronto and the GTA, please refer to our article Parking Space Dimensions in Toronto and the GTA: Zoning Standards and Design Guide.

Design Approach Based on the Age of the House

House Condition
Code Path
Design Considerations
Existing house (over 5 years)
Part 11
Some flexibility but fire safety must be addressed.
New house or major renovation
Part 9
Full compliance with current code required.
Three or more units
Small Building
More complex design and fire protection required.

Why Professional Design Is Important

A legal ARU project requires coordination between zoning, architecture, structural engineering, mechanical design and permit approvals. Proper design reduces delays and ensures compliance with Ontario regulations.

Additional Residential Unit Design Services

Deltoid Consulting provides architectural and engineering services for ARUs, secondary suites and residential conversions across Ontario, including zoning review, permit drawings and construction support.

About the Author

Mehdi Hamedani, P.Eng. is the Principal Engineer and founder of Deltoid Consulting Inc., a multidisciplinary engineering and design firm providing structural, architectural, mechanical, electrical, and building permit consulting services throughout Ontario.

Mehdi is a licensed Professional Engineer in Ontario with extensive experience in residential, commercial, institutional, and industrial projects. His areas of expertise include structural engineering, building permit approvals, Ontario Building Code compliance, restaurant design, additional residential units (ARUs), custom homes, and commercial renovations.

Through the Deltoid Consulting Resources page, Mehdi shares practical guidance on engineering, building permits, zoning regulations, and construction requirements to help property owners, business owners, contractors, and developers better understand the design and approval process.

Deltoid Consulting Inc.
30 Fulton Way, Unit 8, Suite 100
Richmond Hill, ON L4B 1E6
Phone: (416) 427-2720
Email: info@deltoidconsulting.com
Website: www.deltoidconsulting.com